1.- In the case of Rehabilitations, remodeling and Divisions, the complexity depends on:
Low: Construction or demolition of walls up to 6 ml, extensions up to 10 m²
Medium: Construction or demolition of walls up to 12 ml, extensions up to 15 m²
High: Construction or demolition of walls over 12 ml, extensions over 15 m²
2.- In the rest of the cases the complexity and the rates must be corresponding:
Low: Up to 60 m²
Average: Between 60 and 80 m²
High: more than 80 m²
3.- In the case where a feasibility study is not carried out, this is NOT charged.